The client required that all primary and secondary beams were EXACTLY 600mm deep. The secondary beams were ex 457x152x52kg/m, with a 10mm pre camber. The primary beams were simply 610x229x101kg/m UB with profiled cells.
Fabricator: Bone Steel Ltd Engineer: BSC.P Leeds Span: 12m x 6m grid Beam: 600 x 152 x 52kg/m
|